Current Dev Position: YP 2.2 M1
Next Deadline: YP 2.2 cut off: June 13, 2016
SWAT team rotation: Juro -> Anibal
https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
Key Status/Updates:
* The bitbake python3 branch is nearing readiness, the OE-Core branch is not quite at the same level of cleanliness but has the functionality and just needs cleanup. Known issues remaining are toaster and various tools in scripts/, help in testing would be most welcome as we have found several distro specific issues so far.
* With python3, basic image execution is known to work, as is testimage (qemu runtime testing) and basic oe-selftests.
* We have various significant changes from Khem such as gcc 6, glibc upgrade and so on. A portion of these have merged into master, the rest should enter -next for testing over the weekend.
* We now have automated BuildLog generation in the wiki to help our build triage (SWAT) process which starts the process improvements planned in 2.2 (thanks Joshua!)
* There was a nice cleanup to staging.bbclass from Peter (thanks!)
* There is a good discussion happening on the architecture list about trying to come up with a standardized way of defining builds and possibly handling layer checkout. Please join the discussion if interested.
* WDD continues to rise :(
* YP 1.8.2 is now in QA
* meta-intel 5.0 should finish QA today
Key YP 2.2 Dates:
* YP 2.2 M1 cut off would be: 6/13/16
* YP 2.2 M1 release would be: 6/24/16
* YP 2.2 M2 cut off would be: 7/18/16
* YP 2.2 M2 release would be: 7/29/16
* YP 2.2 M3 cut off would be: 8/29/16
* YP 2.2 M3 release would be: 9/9/16
* YP 2.2 M4 cut off would be: 10/3/16
* YP 2.2 M4 release would be: 10/28/16
Tracking Metrics:
WDD 2618 (last week 2532)
(https://wiki.yoctoproject.org/charts/combo.html)
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.2_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.2_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.2_Features
[If anyone has suggestions for other information you'd like to see on this weekly status update, let us know!]
Thanks,
Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
* Work Telephone: (503) 712-0534
* Cell: (208) 244-4460
* Email: stephen.k.jolley at intel.com
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.yoctoproject.org/pipermail/yocto/attachments/20160513/6e319b77/attachment.html>
More information about the yocto
mailing list