[yocto] Yocto Project Status WW23’17
Jolley, Stephen K
stephen.k.jolley at intel.com
Mon Jun 5 07:48:39 PDT 2017
Current Dev Position: Preparing for YP 2.4 M1
Next Deadline: YP 2.4 M1 Cut off is June 12, 2017
SWAT team rotation: Anibal -> Todor on June 2, 2017.
SWAT team rotation: Todor -> Alejandro on June 9, 2017.
https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
Key Status/Updates:
· Morty YP 2.2.2 is due out of QA imminently. QA report so far is available at: https://wiki.yoctoproject.org/wiki/2.2_QA_Status#Summary_Report
· There are a couple of issues there which may mean we respin YP 2.2.2 (Morty) and take it to an rc2.
· Krogoth YP(2.1.3) builds remain broken for no-x11 and musl.
· pyro 2.3.1 CVE backport work is still remaining.
· oe-selftest and rpm performance improvements aren’t quite ready yet and pending revised patches.
· A stable maintainer for the pyro series needs to be appointed. Armin has offered but has already taken on a number of releases. If anyone else is interested, please talk to Richard.
Planned upcoming dot releases:
YP 2.1.3 Cut off May 22, 2017 - Running late due to issues.
YP 2.1.3 Release by June 3, 2017
YP 2.3.1 Cut off May 30, 2017 - Running late due to issues.
YP 2.3.1 Release by June 9, 2017
YP 2.2.2 Cut off June 5, 2017 - Put into QA early.
YP 2.2.2 Release by June, 16 2017
YP 2.3.2 Cut off Aug 7, 2017
YP 2.3.2 Release by Aug. 18, 2017
Key YP 2.4 Dates are:
YP 2.4 M1 Cut off is June 12, 2017
YP 2.4 M1 Release by June 23, 2017
YP 2.4 M2 Cut off is July 17, 2017
YP 2.4 M2 Release by July 28, 2017
YP 2.4 M3 Cut off is Aug. 21, 2017
YP 2.4 M3 Release by Sept. 1, 2017
YP 2.4 M4 (Final) Cut off is Sept. 18, 2017
YP 2.4 M4 (Final) Release by Oct. 20, 2017
Tracking Metrics:
WDD 2793 (last week 2797)
(https://wiki.yoctoproject.org/charts/combo.html)
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.4_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.4_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.4_Features
[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]
Thanks,
Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
• Work Telephone: (503) 712-0534
• Cell: (208) 244-4460
• Email: stephen.k.jolley at intel.com
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.yoctoproject.org/pipermail/yocto/attachments/20170605/d914f1cf/attachment.html>
More information about the yocto
mailing list