Current Dev Position: Preparing for YP 2.4 M2
Next Deadline: YP 2.4 M2 Cut off is July 17, 2017
SWAT team rotation: Stephano -> Maxin on June 30, 2017.
SWAT team rotation: Maxin -> Cal on July 7, 2017.
https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
Key Status/Updates:
· YP 2.4 M1 is due to be released.
· YP 2.1.3 rc2 (krogoth) is in QA, mainly to provide checks on the new autobuilder cluster publishing capabilities. It is mostly complete see: https://wiki.yoctoproject.org/wiki/2.1_QA_Status#Summary_Report
· YP 2.2.2 (Morty) continues to have issues with sanity tests failing for mips/aarch64 preventing a building making it to QA.
· We’ve merged changes which deviate us more significantly from the LSB than we have in the past. Since LSB is in maintenance mode and not targeted to Embedded/IoT usages this seems appropriate and the differences are documented in README.lsb.
· General patches are merging but triage of patches failing various tests is still the limiting factor on things merging.
· Bugzilla cleanup is ongoing however assistance on cleanup of bugs, particularly the older languishing ones would be much appreciated. This is having a positive effect on the bug tracking metrics (see the link below).
Planned upcoming dot releases:
YP 2.1.3 Cut off May 22, 2017 - In QA now.
YP 2.1.3 Release by June 3, 2017
YP 2.2.2 Cut off June 5, 2017 - See status above, working for an rc2.
YP 2.2.2 Release by June, 16 2017
YP 2.3.1 Cut off May 30, 2017 - Running late, but rc1 should go into QA after YP 2.1.3, and YP 2.2.2 are done.
YP 2.3.1 Release by June 9, 2017
YP 2.3.2 Cut off Aug 7, 2017
YP 2.3.2 Release by Aug. 18, 2017
Key YP 2.4 Dates are:
YP 2.4 M2 Cut off is July 17, 2017
YP 2.4 M2 Release by July 28, 2017
YP 2.4 M3 Cut off is Aug. 21, 2017
YP 2.4 M3 Release by Sept. 1, 2017
YP 2.4 M4 (Final) Cut off is Sept. 18, 2017
YP 2.4 M4 (Final) Release by Oct. 20, 2017
Tracking Metrics:
WDD 2508 (last week 2602)
(https://wiki.yoctoproject.org/charts/combo.html)
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.4_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.4_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.4_Features
[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]
Thanks,
Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
• Work Telephone: (503) 712-0534
• Cell: (208) 244-4460
• Email: stephen.k.jolley at intel.com
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.yoctoproject.org/pipermail/yocto/attachments/20170630/1821ec2d/attachment.html>
More information about the yocto
mailing list